Foundation of the Hellenic World - Virtual Reality
Kivotos (ReaCTor) relocation: September - November, 2002
managed by Maria Roussou - Head of VR Department, 09/98 - 12/02


..............
............1...........
..........2............
...........3............
...........4............
...........5............
.
.................
07.08.2002

site survey & measurements

.........................
........................
.........................
........................
........................
.

11.09.2002

construction of new site

.........................
.........................
..........................
.........................
.........................
.

19.09.2002

dry walls installed

.........................
.........................
..........................
.........................
.........................
.

20.09.2002


beginning of ReaCTor floor construction

.........................
.........................
.........................
.........................
.........................
.

07.10.2002

measurements for floor base & cables

.........................
.........................
.........................
.........................
.........................
.

08.10.2002

tools arrive,
proj. 1,2,3 removed,
base painted,
area cleaned


.........................
.........................
.........................
.........................
.........................
.

09.10.2002

SGI site survey,
lino delivered,
screens covered for move

.........................
.........................
.........................
.........................
.........................
.

10.10.2002

hole in wall,
speakers removed,
screens moved






.



screen #1 moved










screen #1 moved


screen #1 moved


screen #2 moved


screen #2 moved


screen #3 moved


screen #3 moved


proj. 4 unmounted

.........................
..........................
.........................
.........................
.........................
.

11.10.2002

structure dismantle, linoleum laid

..........................
..........................
..........................
..........................
..........................
.

14.10.2002
.
.

.
.
structure rebuilt, proj. retubing, speakers

.........................
..........................
..........................
..........................
..........................

15.10.2002

structure rebuilt, screens installed, proj. 4

.........................
..........................
..........................
..........................
..........................
.

16.10.2002 17.10.2002
18.10.2002
reactor
control room
reactor

reactor
.
.

.
.
structure rebuilt top mirror in place, Intersense installed

.........................
..........................
..........................
..........................
..........................
.

21.10.2002
31.10.2002
onyx move
reactor
reactor
reactor
onyx reloc
.
.

.
.
ONYX moved, ceiling made & attached,
cold room cooling system, projector retubing

.........................
..........................
.......................... .......................... ..........................
.


onyx reloc
onyx reloc
onyx reloc
onyx reloc
onyx reloc
.
.

.
.


.........................
..........................
..........................
..........................
..........................


01.11.2002
10.11.2002

onyx reloc
onyx reloc
onyx reloc



Intersense testing and program adjustments to new tracker

.........................
..........................
..........................
..........................
..........................


12.11.2002
completed space
completed space
completed space
completed space
completed space
.
.

.
.
New space completed

.........................
..........................
..........................
..........................
..........................


15.11.2002
completed space
completed space
completed space
completed space
completed space
.
.

.
.
Opening

.........................
..........................
..........................
..........................
..........................



completed space
completed space
completed space
completed space
completed space

.........................
..........................
..........................
..........................
..........................


FHW | VR ©2002, M. Roussou